ContID   262054   EST NO  0001

Date:08/26/2026

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 262054 Estimate Number 0001 Estimate Type DRAFT_PROGRESS
District Office PIKEVILLE (12340)  Smith, Brittany A. (Hamilton)

Contractor MOUNTAIN ENTERPRISES INC MARS ADDR SN 0
PO 13130
LEXINGTON , KY , 40583-3130
Pay Period 02/18/2026  TO  08/21/2026
Date Approved 08/25/2026
Primary Proj Number MP06001602601
Project No. FD05 060 0160 000-004, FD05 060 0582 000-004
Primary County KNOTT
Name of Road KY 160 & KY 582 IN KNOTT COUNTY
Description BEGIN AT KY 15 EXTENDING NORTH TO EXISTING PAVEMENT JOINT 74 FEET NORTH OF KY 582
     
     
Date Let 01/29/2026 Formal Acceptance
Date Awarded 02/10/2026 Date Work Began
Date Contract Executed 02/18/2026 Open To Traffic
Date NTP Issued 02/18/2026 Actual Completion Date

Current Contract Amount

$1,212,608.27

Total to Date

Prev to Date

This Estimate

Original Amount

$1,212,608.27

Total Earnings

$7,752.00

$0.00

$7,752.00

Percent Complete

0.64

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$1,204,856.27

Gross Earnings

$7,752.00

$0.00

$0.00

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$7,752.00

$0.00

7,752.00

Contract Id 262054

Change Order Summary

County KNOTT
Estimate Nbr 0001 Project Number FD05 060 0160 000-004, FD05 060 0582 000-004
Contractor MOUNTAIN ENTERPRISES INC Period 02/18/2026  TO  08/21/2026
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 262054

COMMONWEALTH OF KENTUCKY

County KNOTT
Contract Type PALT   PAVEMENT (WITH ALTERNATES)

TRANSPORTATION CABINET

Primary Project Number MP06001602601
Estimate Nbr 0001 Period 02/18/2026  TO  08/21/2026
Contractor MOUNTAIN ENTERPRISES INC
 
Project MP06001602601 Fed/State Project Number FD05 060 0160 000-004 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0080 TEMPORARY SIGNS 02562 SQFT 350.00 350.000 299.500 0.000 299.500 17.00 5,091.50 5,091.50
0085 MAINTAIN & CONTROL TRAFFIC (KY 160) 02650 LS 1.00 1.000 0.000 0.000 8,500.00 0.00
0090 EDGELINE RUMBLE STRIPS 02697 LF 35,200.00 35,200.000 0.000 0.000 0.20 0.00
0095 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 36,900.00 36,900.000 0.000 0.000 0.18 0.00
0100 PAVE STRIPING REMOVAL-6 IN 06531 LF 73,800.00 73,800.000 0.000 0.000 0.45 0.00
0105 PAVE STRIPING-THERMO-6 IN W 06542 LF 36,900.00 36,900.000 0.000 0.000 1.10 0.00
0110 PAVE STRIPING-THERMO-6 IN Y 06543 LF 36,900.00 36,900.000 0.000 0.000 1.10 0.00
0115 PAVE MARKING-THERMO STOP BAR-24IN 06568 LF 24.00 24.000 0.000 0.000 14.00 0.00
0120 CENTERLINE RUMBLE STRIPS 20458ES403 LF 17,540.00 17,540.000 0.000 0.000 0.18 0.00
0125 POLYMER ASPHALT EMULSION FOR SCRUB SEAL 24858EC TON 103.00 103.000 0.000 0.000 810.00 0.00
0130 ASPHALT SEAL AGGREGATE - TYPE D 24961EC SQYD 66,252.00 66,252.000 0.000 0.000 1.27 0.00
Project MP06001602601 Fed/State Project Number FD05 060 0160 000-004 Category 0003 THINLAY
0145 LEVELING & WEDGING PG64-22 00190 TON 395.00 395.000 0.000 0.000 132.25 0.00
0150 ASPHALT MATERIAL FOR TACK 00356 TON 32.00 32.000 0.000 0.000 10.00 0.00
0155 MOBILIZATION FOR MILL & TEXT (KY 160) 02676 LS 1.00 1.000 0.000 0.000 2,750.00 0.00
0160 ASPHALT PAVE MILLING & TEXTURING 02677 TON 70.00 70.000 0.000 0.000 185.25 0.00
0165 CL2 ASPH SURF NO.4D PG64-22 21653ES403 TON 2,280.00 2,280.000 0.000 0.000 137.35 0.00
Project MP06001602601 Fed/State Project Number FD05 060 0160 000-004 Category 0004 DEMOBILIZATION
0170 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 8,962.51 0.00
SUBTOT

$5,091.50

$5,091.500

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

0.00

$0.000

 

 

 

Project MP06005822601 Fed/State Project Number FD05 060 0582 000-004 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0005 TEMPORARY SIGNS 02562 SQFT 350.00 350.000 156.500 0.000 156.500 17.00 2,660.50 2,660.50
0010 MAINTAIN & CONTROL TRAFFIC (KY 582) 02650 LS 1.00 1.000 0.000 0.000 8,500.00 0.00
0015 EDGELINE RUMBLE STRIPS 02697 LF 39,600.00 39,600.000 0.000 0.000 0.20 0.00
0020 PAVE STRIPING-TEMP PAINT-4 IN 06510 LF 44,100.00 44,100.000 0.000 0.000 0.18 0.00
0025 PAVE STRIPING-PERM PAINT-6 IN 06515 LF 81,200.00 81,200.000 0.000 0.000 0.26 0.00
0030 POLYMER ASPHALT EMULSION FOR SCRUB SEAL 24858EC TON 88.00 88.000 0.000 0.000 810.00 0.00
0035 ASPHALT SEAL AGGREGATE - TYPE D 24961EC SQYD 56,939.00 56,939.000 0.000 0.000 1.27 0.00
Project MP06005822601 Fed/State Project Number FD05 060 0582 000-004 Category 0003 THINLAY
0050 LEVELING & WEDGING PG64-22 00190 TON 193.00 193.000 0.000 0.000 132.25 0.00
0055 ASPHALT MATERIAL FOR TACK 00356 TON 24.00 24.000 0.000 0.000 10.00 0.00
0060 MOBILIZATION FOR MILL & TEXT (KY 582) 02676 LS 1.00 1.000 0.000 0.000 2,750.00 0.00
0065 ASPHALT PAVE MILLING & TEXTURING 02677 TON 30.00 30.000 0.000 0.000 185.25 0.00
0070 CL2 ASPH SURF NO.4D PG64-22 21653ES403 TON 1,970.00 1,970.000 0.000 0.000 137.35 0.00
Project MP06005822601 Fed/State Project Number FD05 060 0582 000-004 Category 0004 DEMOBILIZATION
0075 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 8,962.49 0.00
SUBTOT

$2,660.50

$2,660.500

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

0.00

$0.000